We have a MSProject 2003 installation, where one project do some tricky stuff.
We had one project which was saved under a new name. Now in the timesheet
website, all task have 0 hour work for all days. The total is fine though
I tried republish tasks, but this wont fill in on which days who used how
many hours. Only the total is displayed in the timesheet view.

Now. If I open the project from the MS project 2003 office application, I
can see on which days how many hours is registred.

How can this be, and can I update the timesheet view somehow?

Thanks
Christian
 
M

Mike Glen

Hi Christian,

It sounds like you're using Project Server. Try posting on the
microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen