P
Peter Rooney
It's that man again! My plan consists of a number of discrete projects, each
of which contains tasks and sub tasks performed by one of four teams within
the department thus:
Project1
Team1
Tasks
Sub Tasks
Team2
Tasks
Sub Tasks
Project 2
Team1
Sub Tasks
etc etc
I need to create a seperate plan for each of the four teams by copying and
pasting their tasks within each project. I can filter the plan to only show
each team's tasks, but when I copy, I get all the tasks in between (i.e. for
all the other teams) too.
Is there any way in which I can copy only the tasks and sub tasks that are
displayed by the filtering?
Once again, looking forward to your help!
Pete
of which contains tasks and sub tasks performed by one of four teams within
the department thus:
Project1
Team1
Tasks
Sub Tasks
Team2
Tasks
Sub Tasks
Project 2
Team1
Sub Tasks
etc etc
I need to create a seperate plan for each of the four teams by copying and
pasting their tasks within each project. I can filter the plan to only show
each team's tasks, but when I copy, I get all the tasks in between (i.e. for
all the other teams) too.
Is there any way in which I can copy only the tasks and sub tasks that are
displayed by the filtering?
Once again, looking forward to your help!
Pete