I was wondering if anyone had some advice on duplicating task links with
their timing and lag.

We repeat the same group of tasks, with essentially the same timing and lag
between tasks.

Is there a way to reproduce this? (Something similar to the copy/paste
function in Excel, where the program is smart enough to sum an adjacent
column when the formula is copied & pasted into an adjacent cell).

Thank you
 
J

Jan De Messemaeker

Hi,

Select the group of tasks by their ID (the whole task image now blackens)
Copy, Paste.
All predecessors WITHIN THE SUBSET are now adapted.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 