J
Jrufin
Hi,
Our corporate financial calendar is structured in this way:
JAN 2008 (from Jan 1 to 25)
FEB 2008 (from Jan 26 to Feb 22)
MAR 2008 (from Feb 23 to Mar 28)
and so on....
Question is, how can I change teh calendar in MPP so taht it is the same as
our financial calendar? Currently the calendar in project is defaulted to the
"normal" calendar, January is 1st to 31st, etc.....
The reason why I need this is for the financials reporting of the projects
costs, resource cost with emphasis on our fiscal financial calendar. Pls
help!
Thanks.
Our corporate financial calendar is structured in this way:
JAN 2008 (from Jan 1 to 25)
FEB 2008 (from Jan 26 to Feb 22)
MAR 2008 (from Feb 23 to Mar 28)
and so on....
Question is, how can I change teh calendar in MPP so taht it is the same as
our financial calendar? Currently the calendar in project is defaulted to the
"normal" calendar, January is 1st to 31st, etc.....
The reason why I need this is for the financials reporting of the projects
costs, resource cost with emphasis on our fiscal financial calendar. Pls
help!
Thanks.