N
Nikki
Can you tell me the correct setup for this situation?
Example:
I have 3 people that decorated a Christmas tree
This had to be done sometime between Nov 8 and Nov. 24.
It took 2 hours to accomplish.
If I put 2 hours in duration it will not let me put the Nov 8-Nov 24 in
Start and finish
If I put 2 hours in work it will not figure that 3 people worked on it so it
was really 6 hours of work.
Is there a task type I can use for this? Or do I have to do the math myself
and put 6 hours in the work column?
Thanks for any help you can give!!!
-
Thanks,
Nikki
Example:
I have 3 people that decorated a Christmas tree
This had to be done sometime between Nov 8 and Nov. 24.
It took 2 hours to accomplish.
If I put 2 hours in duration it will not let me put the Nov 8-Nov 24 in
Start and finish
If I put 2 hours in work it will not figure that 3 people worked on it so it
was really 6 hours of work.
Is there a task type I can use for this? Or do I have to do the math myself
and put 6 hours in the work column?
Thanks for any help you can give!!!
-
Thanks,
Nikki