Correcting mis-keyed timesheets in Project Server 2007 after submitted

A

anovak

Say a timesheet manager overlooks an error or for logistics sake, we
make everyone their own timesheet manager (auto approval in that case)
and time has already been submitted and approved.

Is it possible for the resource to change the time

1. Once submitted?
2. Once approved?

If not, is it a matter of the PM or RM manually adjusting the
information in the project plan after task updates are applied?

Thanks
Andy Novak
UNT
 
M

Marc Soester [MVP]

Hi annovak,

Yes a timesheet can be changed after it has been submitted and approved.
Within the timesheet function you have an option to "recall" a timesheet.
This options allows you to change a timesheet after it has been approved.

I hope this helps
 
A

anovak

Hi annovak,

Yes a timesheet can be changed after it has been submitted and approved.
Within the timesheet function you have an option to "recall" a timesheet.
This options allows you to change a timesheet after it has been approved.

I hope this helps

Thanks Marc. Works fine.
 
D

Dale Howard [MVP]

Andy --

The resource can recall his/her Timesheet in either case, correct it, and
resubmit it for approval. Hope this helps.
 