Correcting Timesheet after project is corrupted

J

JodyJ

I had a project that was corrupted. I saved it as an XML file and reimported
it to Project Server. All is well, except.....the actual hrs in my plan are
correct but the hrs on timesheets of resources aren't accurate. Is there a
way to get timesheets corrected to avoid confusion?
 
D

Dale Howard [MVP]

JodyJ --

I'm assuming your Project Server administrator deleted the original
corrupted project in the Project Server database. If this is the case, here
is what you should do with the new version of the project:

1. Open it
2. Click Collaborate - Publish - Republish Assignments
3. Select the "Overwrite actual work entered by resources" option
4. Click OK

Doing so will "push" the Actual Work from the project plan to each user's
timesheet in PWA. Hope this helps.
 