N
Nitesh
Hi all
I’m using Project Professional 2003 & Project Web Access 2003. I’m facing
a problem regarding Portfolio analyzer data. The Portfolio analyzer is not
showing proper data for Work, Actual Work, and Baseline Work for projects
plans. As still data is available & display in project central page (Project
Web Access) and in Project Professional but portfolio display as zero (but
not for all project plans, only few of them) means some of project data is
missing and display as zero.
I don’t know what is happening because Project plans updating properly,
resources can log their efforts properly & their efforts are updated properly
in project plan.
OLAP cube is scheduled to build at 1:00 AM morning and its updated
successfully on daily basis.
Please suggest what to do so that we use correct data for our analysis
purpose.
I’m using Project Professional 2003 & Project Web Access 2003. I’m facing
a problem regarding Portfolio analyzer data. The Portfolio analyzer is not
showing proper data for Work, Actual Work, and Baseline Work for projects
plans. As still data is available & display in project central page (Project
Web Access) and in Project Professional but portfolio display as zero (but
not for all project plans, only few of them) means some of project data is
missing and display as zero.
I don’t know what is happening because Project plans updating properly,
resources can log their efforts properly & their efforts are updated properly
in project plan.
OLAP cube is scheduled to build at 1:00 AM morning and its updated
successfully on daily basis.
Please suggest what to do so that we use correct data for our analysis
purpose.