L
Lindy
Hi,
We're using Project Pro 2007 w/PWA and started seeing some problems as soon
as we began using Task Updates:
Saving from the client to the server takes a long time (>4 min) - it seems
to get stuck at 84% for several minutes. Then when we click Publish it often
tells us we need to Save before we can Publish - sometimes we have to go thru
this cycles 4 times to publish!
Our user's Notes from PWA doesn't alway make it over to the Project client
when we accept task updates.
The Preview function doesn't work at all in Task Updates - it highlights
tasks that have nothing to do with the Update.
And strangest of all - when we open the project on the client, the Finish
dates for certain COMPLETED tasks are changed to dates way in the future like
2012. We correct those dates, Save, Publish... and then sometime later when
we open the project on the client the same completed tasks have changed
Finish dates again!
Our IT guy says it's a corrupt db and advised us to re-create the Project
Plan from scratch and republish it. That's a lot of work. We wouldn't mind if
we knew it would solve the problem, but we're afraid we'll see the same
issues in the new version.
Any advice?
Many thanks,
We're using Project Pro 2007 w/PWA and started seeing some problems as soon
as we began using Task Updates:
Saving from the client to the server takes a long time (>4 min) - it seems
to get stuck at 84% for several minutes. Then when we click Publish it often
tells us we need to Save before we can Publish - sometimes we have to go thru
this cycles 4 times to publish!
Our user's Notes from PWA doesn't alway make it over to the Project client
when we accept task updates.
The Preview function doesn't work at all in Task Updates - it highlights
tasks that have nothing to do with the Update.
And strangest of all - when we open the project on the client, the Finish
dates for certain COMPLETED tasks are changed to dates way in the future like
2012. We correct those dates, Save, Publish... and then sometime later when
we open the project on the client the same completed tasks have changed
Finish dates again!
Our IT guy says it's a corrupt db and advised us to re-create the Project
Plan from scratch and republish it. That's a lot of work. We wouldn't mind if
we knew it would solve the problem, but we're afraid we'll see the same
issues in the new version.
Any advice?
Many thanks,