Corrupt Project Files

J

JohnJ

Are there any strategies or tools for cleaning up potentially corrupt project
files in Project Server 2003?
 
D

Dale Howard [MVP]

JohnJ --

The general process is this:

1. Save the corrupted file as an .xml file and close the file
2. Ask your Project Server administrator to delete the project from the
Project Server database
3. Open the .xml project file
4. Click File - Save As and save the file as an .mpp file
5. Import the .mpp file into the Project Server database using Tools -
Enterprise Options - Import Project to Enterprise

Refer to the following FAQ for the steps needed to delete the project
without deleting its SharePoint subweb:

http://www.projectserverexperts.com/Shared Documents/DeleteProjectWithoutSubweb.htm

Hope this helps.
 
B

Bart

Hi,
Just a remark.
If you are working with Managed periods, the procedure is lsightky more
complex because of restriction to push actuals from the client to the server.
Bart Willem

Dale Howard said:
JohnJ --

The general process is this:

1. Save the corrupted file as an .xml file and close the file
2. Ask your Project Server administrator to delete the project from the
Project Server database
3. Open the .xml project file
4. Click File - Save As and save the file as an .mpp file
5. Import the .mpp file into the Project Server database using Tools -
Enterprise Options - Import Project to Enterprise

Refer to the following FAQ for the steps needed to delete the project
without deleting its SharePoint subweb:

http://www.projectserverexperts.com/Shared Documents/DeleteProjectWithoutSubweb.htm

Hope this helps.
 
D

Dale Howard [MVP]

Bart --

Yes, the Managed Time Periods feature needs to be temporarily disabled to
allow the PM to republish the assignments for the imported project. Thanks!




Bart said:
Hi,
Just a remark.
If you are working with Managed periods, the procedure is lsightky more
complex because of restriction to push actuals from the client to the
server.
Bart Willem
 
J

JohnJ

We are using managed periods. I tried the process with a project on our test
server. All the actuals came back fine and I was able to reestablish
timesheets and progress the schedule per usual. Is there something in
particular that I should be looking for? I have yet to try the process on a
larger project in production.
--
John Jaeger
SacDOT PMO


Bart said:
Hi,
Just a remark.
If you are working with Managed periods, the procedure is lsightky more
complex because of restriction to push actuals from the client to the server.
Bart Willem
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top