S
Shawn Everingham
I think there is a post running around here that discusses corrupt tasks in
MSPS 2007.
I want to share my ongoing issue as an administrator and don't know all the
implications of how we are "working around" the corrupted tasks.
So, here goes....
Firstly, A task is orginated and resources are applied. Two weeks or
sometime after actuals are applied, another resource is added to the task.
The project is saved and published. The resource that was added to the task
that had existing work, that resource complains of not being able to get to
"my tasks". Sure enough, a query that was posted here that reveals corrupt
tasks in MSPS 2007, shows that the task is indeed corrupt, yet only for the
added resource.
So...my fix is to create a duplicate task, remove the offending resource
from the corrupt task, and add them to the duplicated task, saving and
publishing the project. Is this the correct work around to be used?
Another similar situation involves a corrupt task in which the cause of the
corruption of the task is unknown. The task has original resources assigned
to it, with actuals applied. I have been successful in copying the task and
pasting it below the original task and then deleting the original task.
Problem is, actual work seems to get lost. Is there a way to keep actual work
in this situation? thanks!
--Technology, like art, is a soaring stretch of our imagination...Daniel
Bell. 1919
MSPS 2007.
I want to share my ongoing issue as an administrator and don't know all the
implications of how we are "working around" the corrupted tasks.
So, here goes....
Firstly, A task is orginated and resources are applied. Two weeks or
sometime after actuals are applied, another resource is added to the task.
The project is saved and published. The resource that was added to the task
that had existing work, that resource complains of not being able to get to
"my tasks". Sure enough, a query that was posted here that reveals corrupt
tasks in MSPS 2007, shows that the task is indeed corrupt, yet only for the
added resource.
So...my fix is to create a duplicate task, remove the offending resource
from the corrupt task, and add them to the duplicated task, saving and
publishing the project. Is this the correct work around to be used?
Another similar situation involves a corrupt task in which the cause of the
corruption of the task is unknown. The task has original resources assigned
to it, with actuals applied. I have been successful in copying the task and
pasting it below the original task and then deleting the original task.
Problem is, actual work seems to get lost. Is there a way to keep actual work
in this situation? thanks!
--Technology, like art, is a soaring stretch of our imagination...Daniel
Bell. 1919