J
Jan M.
Hello,
There are 25 projects in our database. Cube data is correct for all projects
exept one:
Work reads 74 000 hours instead of 10 000,
Actual work reads 24 000 hours instead of 4 000,
Baseline reads 77 000 hours instead of 12 000.
The cube is built every week and every other project data is updated
correctly, but rebuilding the cube isn't doing any good to this particular
project.
What should be done to get rid of this corrupted data?
Any suggestion would be appreciated.
Thanks.
Jan M.
There are 25 projects in our database. Cube data is correct for all projects
exept one:
Work reads 74 000 hours instead of 10 000,
Actual work reads 24 000 hours instead of 4 000,
Baseline reads 77 000 hours instead of 12 000.
The cube is built every week and every other project data is updated
correctly, but rebuilding the cube isn't doing any good to this particular
project.
What should be done to get rid of this corrupted data?
Any suggestion would be appreciated.
Thanks.
Jan M.