Cost and Actual costs disappear!

I

Ian Howell

Has anyone experienced Cost fields and Actual Cost entries (i.e. non
calculated cost resource assignments) disappearing from an Enterprise Project
file following a save
and publish to project server? The data remains in Project Center Cost view
thus proving it had been saved and published properly but not in the project
file. Is there a location where I can discover all formula which may impact
on these fields?
 
I

Ian Howell

Gary: We are at top level service pack. Further researches would indiciate
that there is a requested hotfix for this known issue. Thanks for your
interest.
 
G

Gary L. Chefetz

Ian:

I don't understand what you mean by "top level." Service packs have numbers
1, 2, etc, and hotfixes have KB numbers and sometimes nicknames like
"Infrastructure Update." I suspect there is an existing fix.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 
E

emailkm

Ian:

I don't understand what you mean by "top level." Service packs have numbers
1, 2, etc, and hotfixes have KB numbers and sometimes nicknames like
"InfrastructureUpdate." I suspect there is an existing fix.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting:http://www.msprojectexperts.com
Project Server Training:http://www.projectservertraining.com
Project Server FAQS:http://www.projectserverexperts.com
Project Server Help Blog:http://www.projectserverhelp.com







- Show quoted text -

Hi Ian - I'm having this same problem. Have you gotten yours resolved
yet???
 