J
jpiedragil
I have a problem with how MS Project is calculating the annual cost for a
resource.
For example, if I have a resource with a Std. Rate of $1,000 per month,
assigned to a task that starts on Jan 01,2010 and ends on Dic 31, 2010, MS
Project calculates an annual cost of $12,428.57, which is different from the
$12,000 I expected.
The task has a fixed duration, I'm using an unmodified Std. Calendar for
2010 and Project is calculating 2,088h o9f work.
Any help will be appreciated.
Best Regards,
Javier
resource.
For example, if I have a resource with a Std. Rate of $1,000 per month,
assigned to a task that starts on Jan 01,2010 and ends on Dic 31, 2010, MS
Project calculates an annual cost of $12,428.57, which is different from the
$12,000 I expected.
The task has a fixed duration, I'm using an unmodified Std. Calendar for
2010 and Project is calculating 2,088h o9f work.
Any help will be appreciated.
Best Regards,
Javier