S
Sylvain (CGI)
Actual setup MS Project 2003 SP 3 connected to Project Server 2003.
The calculation of cost on a fixed work task is not consistant when the
duration of the task if modified manually or by changing the capacity of the
ressource assigned.
For exemple Originaly my task have a duration of 10 days and the calculation
of the cost is OK (ressource rate * work). But when I change the capacity of
the ressource, the duration is modified to a 2 digits décimal (ex: 9.92) and
the cost is loosing cents. For example if I originally have a cost of 5000$
the cost is now at 4998.54. Even if the work hasen't changes.
The calculation of cost on a fixed work task is not consistant when the
duration of the task if modified manually or by changing the capacity of the
ressource assigned.
For exemple Originaly my task have a duration of 10 days and the calculation
of the cost is OK (ressource rate * work). But when I change the capacity of
the ressource, the duration is modified to a 2 digits décimal (ex: 9.92) and
the cost is loosing cents. For example if I originally have a cost of 5000$
the cost is now at 4998.54. Even if the work hasen't changes.