M
M. London
I am using MSP 2003.
Ihave a large project with about 200 tasks and about 35 resources. My tasks
are either fixed duration (most) or fixed units. The resource usage
calculations calculate the work based on the units of each resource and the
duration at the time the resource was added. After that it treats the
calculations on the resource usage page as fixed work. Changes on the gantt
chart of duration or units will be reflected correctly in dates on the gantt
chart, but not on the assignment information table found by double clicking a
taks beneath a resource on the resource usage sheet. That table will show
the dates necessary to maintain the fixed work (different start/end dates
than the gantt chart!!!!). This makes MSP useless for calculating cost if
any changes are made after the initial entries.
How can I fix this?
Ihave a large project with about 200 tasks and about 35 resources. My tasks
are either fixed duration (most) or fixed units. The resource usage
calculations calculate the work based on the units of each resource and the
duration at the time the resource was added. After that it treats the
calculations on the resource usage page as fixed work. Changes on the gantt
chart of duration or units will be reflected correctly in dates on the gantt
chart, but not on the assignment information table found by double clicking a
taks beneath a resource on the resource usage sheet. That table will show
the dates necessary to maintain the fixed work (different start/end dates
than the gantt chart!!!!). This makes MSP useless for calculating cost if
any changes are made after the initial entries.
How can I fix this?