L
lmoritz
The costs were not updating correctly within MSProject when I changed
resource allocations.
I then did an Assignment export out of Project with Duration, Units,
Task and Resource names. I did a calculation of Duration*Unit =
Time... I then did Time*Rate = Cost.
My calculations in excel using the above formula's did not match what
Project had. Most of them were correct but when I add Work to the
export and did it again I noticed that my Time (Duration*Unit)
calculation did NOT match the Work calculation of MS Project.
I am still off somewhere else as well but what would cause this
difference? Is there a bug in Project? All of the Task Types are set
the same.
Any help would be greatly appreciated.
Thank you, Lara
+-------------------------------------------------------------------+
|Filename: ProjSpreadSheetProblem.jpg |
|Download: http://forums.techarena.in/attachment.php?attachmentid=6875|
+-------------------------------------------------------------------+
resource allocations.
I then did an Assignment export out of Project with Duration, Units,
Task and Resource names. I did a calculation of Duration*Unit =
Time... I then did Time*Rate = Cost.
My calculations in excel using the above formula's did not match what
Project had. Most of them were correct but when I add Work to the
export and did it again I noticed that my Time (Duration*Unit)
calculation did NOT match the Work calculation of MS Project.
I am still off somewhere else as well but what would cause this
difference? Is there a bug in Project? All of the Task Types are set
the same.
Any help would be greatly appreciated.
Thank you, Lara
+-------------------------------------------------------------------+
|Filename: ProjSpreadSheetProblem.jpg |
|Download: http://forums.techarena.in/attachment.php?attachmentid=6875|
+-------------------------------------------------------------------+