J
.jussi
I am experiencing a most frustrating and strange behavior from EPM 2007. We
have time-phased fixed costs assigned to certain tasks using a cost resource.
The costs are entered through the resource usage view and the task is set on
the date they are predicted to realize on (a very short task is being used
for these, we'd love to use milestones but they do not retain this
information). These tasks have no other assignments on them and are being
manually maintained by the project managers.
Now while the costs have not been realized the tasks are sitting at 0%
complete. They function as you would expect - the costs are shown in reports
on the date they are predicted and everything works beautifully. Once the
cost is realized, the project manager sets the task as 100% complete and the
fun starts.
After a cost task is complete and a resource submits new hours to the
project, the completed cost tasks duration changes. Not only that, but the
fixed cost assigned to the task using the cost resource (it is entered as a
cost on a certain date) changes too. It would look like the duration is
doubled every time. You can imagine what sort of havoc this wreaks in
reporting actuals.
Has anyone else experienced this? Any ideas how to get around the problem? I
would hate to have to use custom fields to get around this issue.
- Jussi
have time-phased fixed costs assigned to certain tasks using a cost resource.
The costs are entered through the resource usage view and the task is set on
the date they are predicted to realize on (a very short task is being used
for these, we'd love to use milestones but they do not retain this
information). These tasks have no other assignments on them and are being
manually maintained by the project managers.
Now while the costs have not been realized the tasks are sitting at 0%
complete. They function as you would expect - the costs are shown in reports
on the date they are predicted and everything works beautifully. Once the
cost is realized, the project manager sets the task as 100% complete and the
fun starts.
After a cost task is complete and a resource submits new hours to the
project, the completed cost tasks duration changes. Not only that, but the
fixed cost assigned to the task using the cost resource (it is entered as a
cost on a certain date) changes too. It would look like the duration is
doubled every time. You can imagine what sort of havoc this wreaks in
reporting actuals.
Has anyone else experienced this? Any ideas how to get around the problem? I
would hate to have to use custom fields to get around this issue.
- Jussi