Cost changes on one inserted project in master project

P

Peggy Cornett

Project Server (PS) 2007 SP2 MSO
I have a master project (MP) with several inserted projects. The MP is not
stored on PS. It was built by inserting projects from PS and breaking each
link. Calculate is set to manual. I open the MP which has all inserted
projects collasped. I expand one and the cost changes (turns blue) in the
one above it (still collasped). I calculate and it turns back to the number
it was. Why?
These are inserted projects, none of them roll into another.

Also, often a number turns blue but there is no change. I have taken it to
the 13th decimal (in excel) and there is no change. Why does the number turn
blue?
Thanks,
~Spunky
 