Cost column in Ghant View won't recalculate some tasks

S

SShapiro001

I added Cost column to MSP ghant view, then zeroed out some tasks' costs.
Now unable to get MSP to recalculate the proper costs for these tasks even
though the resources haassigned still have all the rate info OK.
 
J

JulieD

Hi

in your gantt chart view - choose view / table:entry / cost to display the
cost table .. .when you zeroed out the cost column project put a negative
value in the fixed cost column ... which you can see when you have the cost
table displayed. Now all you need to do is change these negative fixed
costs to zero and it should work for you.

Regards
JulieD
 