G
Glenn
Hi all,
Is there a way to pull Cost Current, Cost Previous and Cost for Period out
of Project at any point in time?
For example, Cost Current could be the Actual Cost field at the current
Status Date and Cost Previous could be at the last recording period and the
Cost for Period would be the cost from the last recording period minus the
Cost Current.
thanks,
glenn
Is there a way to pull Cost Current, Cost Previous and Cost for Period out
of Project at any point in time?
For example, Cost Current could be the Actual Cost field at the current
Status Date and Cost Previous could be at the last recording period and the
Cost for Period would be the cost from the last recording period minus the
Cost Current.
thanks,
glenn