Hello Anya Blue,
View the cost table and enter the amount against the subtask in the
fixed cost field. By default the cost will be spread on a pro-rated
basis across the task duration. You can view the cost on a
timephased basis in the Task Usage view. Add the cost field to the
right side through Format > Detail Styles.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project