cost error

S

Sam

when i specify the person cost in enter resource pool is $210
but when i open a column cost in project where on different tasks that
resource is assigned .the cost column shows 480 , 630 ,840 on three different
tasks.
i dont understand why the cost has been changed here.

pls reply me soon.
 
B

Ben Howard

Hi Sam, presumably you have entered the cost per hour. If you wanted to
enter the cost per day, then re-enter it as $210/d
 