Hi,

Our Cost field does not display any values on the project summary row of our
master projects in PWA. All other cost fields (e.g., remaining cost, total
cost) display their rollups fine.

We are running 2007 SP2 June CU.

Is there a fix for this?
 
S

ST

I figured out why I was having the problem. I am working in a French version
of Project. In the French version the field "Cout Planifie" translates to
Planned Cost. In fact it was Baseline Cost. With this I figured out that it
was a baseline issue. I fixed it by selecting the Project Summary row of the
master and baselining it with the rollup option.
 