C
CB
I am using MSOP 2007 standard. I have an IMS and a resource pool. I have
all the schedules inserted into the IMS and connected to the RP.
I have Resource A assigned to 2 projects at 50% allocation on each.
However, I have 2 separate rates that I need to apply.
Example
Resource A on project 1 is billed at 10.00
Resource A on project 2 is billed at 12.00
Is there a solution for this scenario?
Thanks.
all the schedules inserted into the IMS and connected to the RP.
I have Resource A assigned to 2 projects at 50% allocation on each.
However, I have 2 separate rates that I need to apply.
Example
Resource A on project 1 is billed at 10.00
Resource A on project 2 is billed at 12.00
Is there a solution for this scenario?
Thanks.