C
Conrad Santiago
I am getting odd results among these fields on the same task:
Cost Rate; Cost; Work
For example on the same task (with a Fixed Cost of 0.00) with the same
resource I get these results:
Cost Rate = 100.00; Cost = 100.00; Work = 1 hr
Cost Rate = 99.80; Cost = 163.00; Work = 1.63 hr
Cost Rate = 100.41; Cost = 164.00; Work = 1.63 hr
In all of these examples, I am simply changing the Work value. In the last
example, I entered 1.64, but it won't display 1.64.
Why is this happening? Any help would be appreciated.
We are using Project Professional 2003 with SP2.
Thanks in advance for any responses.
Conrad Santiago
Cost Rate; Cost; Work
For example on the same task (with a Fixed Cost of 0.00) with the same
resource I get these results:
Cost Rate = 100.00; Cost = 100.00; Work = 1 hr
Cost Rate = 99.80; Cost = 163.00; Work = 1.63 hr
Cost Rate = 100.41; Cost = 164.00; Work = 1.63 hr
In all of these examples, I am simply changing the Work value. In the last
example, I entered 1.64, but it won't display 1.64.
Why is this happening? Any help would be appreciated.
We are using Project Professional 2003 with SP2.
Thanks in advance for any responses.
Conrad Santiago