I need to use a number of contract resources on my project. I have set up the
work resources as well as cost resources for flight, per diem etc. This gives
me a overview of a total cost resouce - is there a way I can allocated the
cost resource to a work resouce?
E.g. - I am using 2 contract resources
Resource 1 accounts for 1 flight (cost resource)
Resouce 2 accounts for 3 flights
So I have a total value of 4 flights - but need to know the split between
the contract resources used. This will give be a better total cost per
resource.
Can it be done?
Thanx
Regards
Tracey
work resources as well as cost resources for flight, per diem etc. This gives
me a overview of a total cost resouce - is there a way I can allocated the
cost resource to a work resouce?
E.g. - I am using 2 contract resources
Resource 1 accounts for 1 flight (cost resource)
Resouce 2 accounts for 3 flights
So I have a total value of 4 flights - but need to know the split between
the contract resources used. This will give be a better total cost per
resource.
Can it be done?
Thanx
Regards
Tracey