C
Cirene
I'm new to Project 2007. I have this...
TASK A / 1.5 days / $1560
- subtask 1 / .5 days / $260
- subtask 2 / .5 days / $260
- subtask 3 / .5 days / $260
TASK A shows the correct sum of the days, but why is the Cost column off? I
would expect it to add up the 3 subtask costs.
TASK A / 1.5 days / $1560
- subtask 1 / .5 days / $260
- subtask 2 / .5 days / $260
- subtask 3 / .5 days / $260
TASK A shows the correct sum of the days, but why is the Cost column off? I
would expect it to add up the 3 subtask costs.