cost /use

R

ruth

hi, in the resource sheet page of MSP, under cost/use , am i expected to put a value there? if yes, is it the addition of standard and overtime rates of each resource?
cheers
 
D

Dale Howard [MVP]

Ruth --

You only need to fill in the Cost/Use field if there is an additional cost
each time the resource is used on the project, in addition to the resource's
standar and overtime rates. For example, I have to pay my plumber a "trip
charge" every time he comes out to my house, along with his hourly billing
rate. The trip charge is an example of a Cost/Use situation. Hope this
helps.




ruth said:
hi, in the resource sheet page of MSP, under cost/use , am i expected to
put a value there? if yes, is it the addition of standard and overtime rates
of each resource?
 