S
Sameer
The problem i have is hard to explain but i will still give it a shot:
When a project Manager creates a project he chooses the Cost Center field
from the project information box, which i defined myself. At the end of the
month the accounts office generates a cube where they can find the cost of
the project.
SO in that case the IT Department gets paid proportional to how much work
they do on a project. This works fine with me.
But now the problem arises: What if a project has multiple Cost Centers, the
requiement is such that 30% of the total cost goes to "x" cost center, 50% to
"y" Cost center and the remaining 20% to "z" cost center.
Do you guys think a Process like this one is possible to achieve with out
custom development?
I need immediate help on this.
Thnx in advance.
Regards
When a project Manager creates a project he chooses the Cost Center field
from the project information box, which i defined myself. At the end of the
month the accounts office generates a cube where they can find the cost of
the project.
SO in that case the IT Department gets paid proportional to how much work
they do on a project. This works fine with me.
But now the problem arises: What if a project has multiple Cost Centers, the
requiement is such that 30% of the total cost goes to "x" cost center, 50% to
"y" Cost center and the remaining 20% to "z" cost center.
Do you guys think a Process like this one is possible to achieve with out
custom development?
I need immediate help on this.
Thnx in advance.
Regards