G
Gav
Hi all,
I am trying to use project 2002 standard to prepare a cost estimate (All
though some at work say it is not an appropriate tool) a
A simple scenario, I have a task that runs over 6 working days (5 day
working week). It has one person who work 8 hour days mon-fri but needs
accommodation for each night including the weekend. So the Accommodation
resource cost needs to be calcualated on elapsed days not duration.
I tried making the accommodation a 24 calendar resource and running it as a
parallel hammock task linked to the start and finish of the workers but the
numbers don't come out as whole days.
Any suggestions. The same problem could occur with renting equipment for a
task on a daily basis with an intervening weekend
Clear as mud?
Cheers
Gav
I am trying to use project 2002 standard to prepare a cost estimate (All
though some at work say it is not an appropriate tool) a
A simple scenario, I have a task that runs over 6 working days (5 day
working week). It has one person who work 8 hour days mon-fri but needs
accommodation for each night including the weekend. So the Accommodation
resource cost needs to be calcualated on elapsed days not duration.
I tried making the accommodation a 24 calendar resource and running it as a
parallel hammock task linked to the start and finish of the workers but the
numbers don't come out as whole days.
Any suggestions. The same problem could occur with renting equipment for a
task on a daily basis with an intervening weekend
Clear as mud?
Cheers
Gav