K
king kong
Hi
I have the following situation (MS-Project 2003):
I have phases with tasks, e.g.
analysis
task 1
task 2
design
task 3
task 4
project management
task 5
task 6
Each phase has a clear end milestone, but group project management
has tasks overlapping the phaes, because I have to do them anyway in
each phase.
for example:
Project reporting 2 hrs per week for the entire project
Now, every tasks has costs budgeted.
If I want to know the costs for phase analysis task 1 and task 2 are
not sufficient.
It needs also the efforts for task 5 and six for the period of time
analysis is executed.
I tried to use a filter with start and end dates but failed to
configure it properly.
I am sure it can be done.
Can you enlighten me how?
Thanks
Kay
I have the following situation (MS-Project 2003):
I have phases with tasks, e.g.
analysis
task 1
task 2
design
task 3
task 4
project management
task 5
task 6
Each phase has a clear end milestone, but group project management
has tasks overlapping the phaes, because I have to do them anyway in
each phase.
for example:
Project reporting 2 hrs per week for the entire project
Now, every tasks has costs budgeted.
If I want to know the costs for phase analysis task 1 and task 2 are
not sufficient.
It needs also the efforts for task 5 and six for the period of time
analysis is executed.
I tried to use a filter with start and end dates but failed to
configure it properly.
I am sure it can be done.
Can you enlighten me how?
Thanks
Kay