CPM - non-dependent tasks

P

petrfanta1

hi everyone,

1) is there a way how to display the critical path set not by the
dependencies but by the leveling as well?
2) is there a way how to display "critical" resources?

detail 1):
let us have 5 tasks, 2 day each assigned to the same resource. with
auto levelling on, they follow one another even without dependencies.
that is ok. but when i display the CP, only the last task is marked as
being part of the CP.

with the "calculate multiple CP" on, i get all of the being on the CP,
true, but the every subgraph is critical, which is not ok

detail 2)
lets have two sets of 5 tasks, all tasks in the first set (A) 2 days
each, all except the second (B) too, the last task being 3 days.
resourceA is assigned to the first set, resourceB assigned to the
second set. is there any report that would show that resourceB is
"critical" (meaning that any delay on tasks with resourceB assigned
will delay the project)?

thanks a lot

(hope the answers are not too abvious for i am a newbie here :)

petr
 
V

vanita

Hi Petr

In netwoking techniques tasks and path are critical, but not resources. What
do you understand by critical resources?

If you want to see resources being used for critical tasks. In the gantt
chart view insert the column for resources and filter the view for critical
activities. Automatically you would see the resources being used by critical
path.

I hope it helps.
Vanita
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top