We have a master project that is made up of 2 inserted projects only. They
are minimized on the saved project. There are no links between the two
subprojects or any other external project. This master saved fine the first
time. However, the next time it was opened and saved, project immediately
crashed. I have since deleted the master and recreated it with the same
results. Any ideas?
 
B

Ben Howard

I have had similiar, it was actually a non-standard calendar assocaited with
a resource on one of the sub plans.

Also, sometimes it is worth saving the plans as XML files, deleting them
from PS2007, and then re-importing them.
 
M

Mike F

Ben,

I am having the same crashing issue when importing projects and then
attemtping to create a master project. What do you mean by "non-standard"
calendar associated with the resource? What calendar should be associated
with a resource in this scenario? We assign a single enterprise calendar for
the project and resources. When I create the master project, I am assigning
the enterprise calendar. Thanks
 