Ravit
Hi,
It seems like when I add new task using the PWA the project is not taking
under consideration the resource base calander.
I will explain-
TheTeam leader enter list of new tasks using the PWA. If for example the new
task duration is 5 days and today is Tuesday I will expect to see in My Task
view the new task with Starting Date on this Tuesday and Finish on the next
Tuesday (since Saturday and Sunday are not working days - this define in the
base calander)
But the real result is that the Finsh is on Saturday.
Is this how it should work?
It seems like when I add new task using the PWA the project is not taking
under consideration the resource base calander.
I will explain-
TheTeam leader enter list of new tasks using the PWA. If for example the new
task duration is 5 days and today is Tuesday I will expect to see in My Task
view the new task with Starting Date on this Tuesday and Finish on the next
Tuesday (since Saturday and Sunday are not working days - this define in the
base calander)
But the real result is that the Finsh is on Saturday.
Is this how it should work?