S
scottbar6
I manage an engineering department and I am looking to use Project to
manage the schedule of my ECO's (Engineering Change Orders). I don't
need each ECO to be an individual project. I am trying to set the
finish no later than date to be the date that I need to release the
change to production. Also each task is not dependent on any other
task. I have the tasks grouped by the engineer that is assigned to
them. Project won't let me drag the task (ECO) in to make the finish
date earlier than the constraint date even though it still meets the
"finish no later than constraint". Help?
manage the schedule of my ECO's (Engineering Change Orders). I don't
need each ECO to be an individual project. I am trying to set the
finish no later than date to be the date that I need to release the
change to production. Also each task is not dependent on any other
task. I have the tasks grouped by the engineer that is assigned to
them. Project won't let me drag the task (ECO) in to make the finish
date earlier than the constraint date even though it still meets the
"finish no later than constraint". Help?