I create my master project by choosing the third option when I open my shared
resource pool so I am sure to pull in all projects using the shared resource
pool.

However, I only want to run reports on this master project, not update the
subprojects and I do not want to prevent others from updating their
subproject while I am doing reporting on the master project.

Is there any way to create a master project with the subprojects set to read
only instead of update? Thanks!
 