E
Eugene Rokhlin
Hi All,
I have got a recordset that keeps some information that needs to be
converted to the MS Project file.
The fields are like these:
- ProjectTaskID
- ProjectTaskParentID
- WBS
- ParentWBS
- TaskName
- StartDate
- EndDate
- .... other non important fields.
What I need to do is to create a .mpp file with correct hierarchy.
So, I know a parent (if any) for every task.
What can I do?
I can open an empty .mpp file. I can add all tasks there. I try then to go
through all the tasks and set a parent for each one. But I can't see the way
to do it.
Do I need to make a task a child or parent of another task at the same time
I add it to the project or is there some way to do it later?
Can I get the task object by its ID or UniqueID?
The hierarchy of tasks can be 3 or more levels deep ....
Thanks.
Best Regards,
Eugene Rokhlin
I have got a recordset that keeps some information that needs to be
converted to the MS Project file.
The fields are like these:
- ProjectTaskID
- ProjectTaskParentID
- WBS
- ParentWBS
- TaskName
- StartDate
- EndDate
- .... other non important fields.
What I need to do is to create a .mpp file with correct hierarchy.
So, I know a parent (if any) for every task.
What can I do?
I can open an empty .mpp file. I can add all tasks there. I try then to go
through all the tasks and set a parent for each one. But I can't see the way
to do it.
Do I need to make a task a child or parent of another task at the same time
I add it to the project or is there some way to do it later?
Can I get the task object by its ID or UniqueID?
The hierarchy of tasks can be 3 or more levels deep ....
Thanks.
Best Regards,
Eugene Rokhlin