O
ozkan ( Turkey )
Hi to everybody;
I try to explain my question with an example.
For example If I have a project and of course some subtask. The project
duration is 30 days and a subtask has 10 days duration, I have assinged a
metarial/cost/work resource to the task; then project automatically
calculated the cash flow depends on the task duration ( 10 days ). But my
real cash flow is different ! I want to spread the flow like 25% of the total
task cost at the begining of the task,15% 30 days later and finaly 55% at the
and of the project.
I couldn't find any way to do it. If someone help me I will be very grateful.
Kind regards
Ozkan KARATAS.
Civ. Engineer ( Turkey )
I try to explain my question with an example.
For example If I have a project and of course some subtask. The project
duration is 30 days and a subtask has 10 days duration, I have assinged a
metarial/cost/work resource to the task; then project automatically
calculated the cash flow depends on the task duration ( 10 days ). But my
real cash flow is different ! I want to spread the flow like 25% of the total
task cost at the begining of the task,15% 30 days later and finaly 55% at the
and of the project.
I couldn't find any way to do it. If someone help me I will be very grateful.
Kind regards
Ozkan KARATAS.
Civ. Engineer ( Turkey )