N
Nick Morrison
Hi Everyone,
I'm looking for a query that will cumulate the weekly baseline work values
that are found in the Task Usage details view. The value is the cumulative
baseline work up to a specific week in time. For example, the week of 10/6
the estimated (baseline) work to be completed on Task 1 is 10 days for the
week, the week of 10/13, 5.5 days of work is estimated to be completed on
Task 1 for a total of 15.5 days. As time goes on, the value gets closer to
the Total Task Baseline work. I think it is stored in the Timephased Data
table, but I'm not sure how to get the data in a usable form. I have looked
at the help files on the Project Server (2003) and in the SDK, but haven't
been able to come up with a solution. Has anyone written a query to obtain
this type of data from the database over a long period of time?
I'm looking for a query that will cumulate the weekly baseline work values
that are found in the Task Usage details view. The value is the cumulative
baseline work up to a specific week in time. For example, the week of 10/6
the estimated (baseline) work to be completed on Task 1 is 10 days for the
week, the week of 10/13, 5.5 days of work is estimated to be completed on
Task 1 for a total of 15.5 days. As time goes on, the value gets closer to
the Total Task Baseline work. I think it is stored in the Timephased Data
table, but I'm not sure how to get the data in a usable form. I have looked
at the help files on the Project Server (2003) and in the SDK, but haven't
been able to come up with a solution. Has anyone written a query to obtain
this type of data from the database over a long period of time?