I have created a MPD with all of my 10 projects, three of them summaries of
the other seven. I have a list of resources in an access databaseI created a
new project in my mpd file that is meant to be the resource pool. I pulled
all the resources from the access database into the resource pool project.
When I open any of the other projects in the MPD, I cannot change the Sharing
option from Use own Resources (i.e. the Use Resources From box is greyed
out). What do I have to do in the MSP_PROJECTS table for the other projects
to see the ResoucePool project.
I tried to change the PROJ_IS_RESOURCE_POOL flag (and the
PROJ_POOL_ATTACHED_TO) fields, but that did not seem to change much.
Any help?
I have created a MPD with all of my 10 projects, three of them summaries of
the other seven. I have a list of resources in an access databaseI created a
new project in my mpd file that is meant to be the resource pool. I pulled
all the resources from the access database into the resource pool project.
When I open any of the other projects in the MPD, I cannot change the Sharing
option from Use own Resources (i.e. the Use Resources From box is greyed
out). What do I have to do in the MSP_PROJECTS table for the other projects
to see the ResoucePool project.
I tried to change the PROJ_IS_RESOURCE_POOL flag (and the
PROJ_POOL_ATTACHED_TO) fields, but that did not seem to change much.
Any help?