Karen --
Since Project Server 2003 does not recognize an "equipment" type of resource
that is any different from a human resource, you have two choices: (1)
create the equipment resource as a Material resource, or (2) create the
equipment resource as a Work resource. If you want to be able to monitor it
across all projects to make sure it does not get overallocated by your PMs,
and to level it if it does become overallocated, you will need to create it
as a Work resource. Hope this helps.