Create Custom Timesheet View

K

Kristi F

Is it possible to create a Custom Timesheet view for a custom group I have
created? I want to publish specific fields that are pertinent to a certain
group to their timesheet view. All the other views listed under Project,
Project Center, Assignment, and Resource Center allow you to copy them, but
not the Timesheet. Also, if you select Add View, there isn't an option for
Timesheet. Does anyone know how to do this?

Thanks
 
J

Jonathan Sofer - MCP

In the current version of Project Server 2003 there is no ability to do
this. I am not sure, but this might be one of the upgrades that MS is
planning on releasing in their P12 version which will only come out for
general use in the summer of 2006 I believe.
 