D
D. Fuhrman
Hi,
I'm new at VBA for Project 2003 (Duh!)
If someone could provide an example of a macro to create one or more
resources and apply values to the cost rate tables, I'd be very grateful.
I've tried various examples from the SDK but I'm getting errors such as
"Expected: end of statement" with little explanation as to what went wrong.
Many thanks in advance.
~ Don
I'm new at VBA for Project 2003 (Duh!)
If someone could provide an example of a macro to create one or more
resources and apply values to the cost rate tables, I'd be very grateful.
I've tried various examples from the SDK but I'm getting errors such as
"Expected: end of statement" with little explanation as to what went wrong.
Many thanks in advance.
~ Don