Hi,
There is no direct way by which one can add WBS field in the create new task
dialog.
However you can make the field appear and check the value of WBS by adding
WBS field in the timesheet of the resources.
This can be done by making use of published fields.
Thanks and Regards,
Manmeet Chaudhari