J
John
I am trying to create a Visual Report that looks similar to the task
usage view so I can compute all resource availability and assigned
work by week or month. I tried creating the report with the Resource
Usage table and selecting the Resource Name, Work, Work Availability,
and Remaining Availability using a resource pool and a master project
but the data is not displaying what I am expecting. The Work
Availability displays daily availability and the work displays the
total worked assigned in one column by I can't seem to get the day by
day or week by week values. Here a week by week snippet of what I
want:
Resource Name 07/29/07 07/30/07 ......12/31/07
Work
Work Availability
Remaining Availability
Does anyone have a solution?
usage view so I can compute all resource availability and assigned
work by week or month. I tried creating the report with the Resource
Usage table and selecting the Resource Name, Work, Work Availability,
and Remaining Availability using a resource pool and a master project
but the data is not displaying what I am expecting. The Work
Availability displays daily availability and the work displays the
total worked assigned in one column by I can't seem to get the day by
day or week by week values. Here a week by week snippet of what I
want:
Resource Name 07/29/07 07/30/07 ......12/31/07
Work
Work Availability
Remaining Availability
Does anyone have a solution?