W
Wesley
Hi
I use the ProjectTaskCreate Method of PDS to create a task in a project
plan. I would like to add values to other fields like "Task Text 1" for
example but can only update the following fields with this method:
<Name></Name>
<Type></Type>
<WBS></WBS>
<OutlineLevel></OutlineLevel>
<Priority></Priority>
<Start></Start>
<Finish></Finish>
<Duration></Duration>
<EffortDriven></EffortDriven>
<Deadline></Deadline>
<Estimated></Estimated>
<Milestone></Milestone>
<Summary></Summary>
<Work></Work>
<PercentComplete></PercentComplete>
<PercentWorkComplete></PercentWorkComplete>
<ActualDuration></ActualDuration>
<ActualWork></ActualWork>
<ActualOvertimeWork></ActualOvertimeWork>
<RemainingDuration></RemainingDuration>
<RemainingWork></RemainingWork>
<RemainingOvertimeWork></RemainingOvertimeWork>
<ConstraintType></ConstraintType>
<ConstraintDate></ConstraintDate>
<LevelAssignments></LevelAssignments>
<LevelingCanSplit></LevelingCanSplit>
<LevelingDelay></LevelingDelay>
<IgnoreResourceCalendar></IgnoreResourceCalendar>
<HideBar></HideBar>
<Rollup></Rollup>
<PhysicalPercentComplete></PhysicalPercentComplete>
<EarnedValueMethod></EarnedValueMethod>
Can I add values to the normal Text fields or is there another method I can
use to update the required fields.
Thanks.
Wesley
I use the ProjectTaskCreate Method of PDS to create a task in a project
plan. I would like to add values to other fields like "Task Text 1" for
example but can only update the following fields with this method:
<Name></Name>
<Type></Type>
<WBS></WBS>
<OutlineLevel></OutlineLevel>
<Priority></Priority>
<Start></Start>
<Finish></Finish>
<Duration></Duration>
<EffortDriven></EffortDriven>
<Deadline></Deadline>
<Estimated></Estimated>
<Milestone></Milestone>
<Summary></Summary>
<Work></Work>
<PercentComplete></PercentComplete>
<PercentWorkComplete></PercentWorkComplete>
<ActualDuration></ActualDuration>
<ActualWork></ActualWork>
<ActualOvertimeWork></ActualOvertimeWork>
<RemainingDuration></RemainingDuration>
<RemainingWork></RemainingWork>
<RemainingOvertimeWork></RemainingOvertimeWork>
<ConstraintType></ConstraintType>
<ConstraintDate></ConstraintDate>
<LevelAssignments></LevelAssignments>
<LevelingCanSplit></LevelingCanSplit>
<LevelingDelay></LevelingDelay>
<IgnoreResourceCalendar></IgnoreResourceCalendar>
<HideBar></HideBar>
<Rollup></Rollup>
<PhysicalPercentComplete></PhysicalPercentComplete>
<EarnedValueMethod></EarnedValueMethod>
Can I add values to the normal Text fields or is there another method I can
use to update the required fields.
Thanks.
Wesley