Create view in Project Server that doesn't re-set to default

H

HMG

Project Server (Office Project Professional 2003 (11.2.2005.1801.15) SP2
Create a new project using the Enterprise Template (set up for us by the guy
who ionstalled Project Server). Different PMs need/want different views.
Select "View"
Select "More Views"
Select "New"
Select "Single view" bullet
Give it a name: HMG GANTT NEW
Screen: GANNT Chart
Table: Choose any, say "Enterprise Entry"
Group: No Group
Filter: All Tasks
Select "Apply"
Make changes to the view - move columns etc
Save it
Close the project
Reopen it.
The New view- HMG GANTT NEW- looks just like the Enterprise default.
What are we doing wrong ?
 
D

Dale Howard [MVP]

HMG --

Your mistake is the Table step when you selected Enterprise Entry. Instead,
select one of Microsoft Project's default tables, make a copy of it and
rename it, then modify the table as desired. Then make sure the new View
references the new table you created. Hope this helps.
 