R
Ray
Hi there. I've used the above function call with a saved template on the
project server and it works well. However while the schedule that came from
the MS Project template looks fine in MS Project 2007, viewing through the
sharepoint Project Center is not so fine.
The tasks are out of order and thus the gantt chart is messed up. Even
clicking on the ID column to try and re-order the tasks does not work as the
task IDs are still out of order or have some 'hidden' order I do not know of.
Anyone ran into this problem before and know what is going on?
I've tried simpler templates but still the same problem.
Much appreciated.
Ray Letts
project server and it works well. However while the schedule that came from
the MS Project template looks fine in MS Project 2007, viewing through the
sharepoint Project Center is not so fine.
The tasks are out of order and thus the gantt chart is messed up. Even
clicking on the ID column to try and re-order the tasks does not work as the
task IDs are still out of order or have some 'hidden' order I do not know of.
Anyone ran into this problem before and know what is going on?
I've tried simpler templates but still the same problem.
Much appreciated.