Creating a custom column to show variance between two date fields?

B

Bill Fuller

I would like to create a custom column that will show the variance (in days)
between an estimated finish date and a baseline date, but don't have a clue
on how to do this. Does anyone have any suggestions on how to do this or
locate info that would be helpful.
 
J

Jan De Messemaeker

Hi,

Insert
Column
Duration1
OK
Tools
Customize
Fields
Select Duration1 (if not already selected)
Click the word Formula
Click Function
Date/Time
Click ProjDateDiff
Replace date1 by the name of the start field f.i.
[Finish7]
Replace date2 by the end field f.i. [Date8]
if you want the difference to be in working days along the project calendar
wipe out ;calendar
OK, OK, etc.

God Luck

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 